I have an NEC form of contract. When do I need to serve an Early Warning Notice?

Morton Fraser Legal Director Julie  Scott-Gilroy
Author
Julie Scott-Gilroy
Legal Director
PUBLISHED:
14 December 2021
Audience:
Real Estate
category:
Article

The NEC suite of contracts is used for a variety of works including engineering and infrastructure projects. For example, an NEC3 Engineering and Construction contract was used for the construction of the London Velodrome for the 2012 Olympics. 

The current version of this suite of contracts is the NEC4. For the purpose of this blog we will use the NEC4 Engineering and Construction Contract, with amendments as at October 2020.

The NEC contract places an emphasis on project management. It requires the contractor to provide a programme of works. The project manager for the contract maintains a risk register which includes any early warning matters.  The early warning procedure is mandatory on both parties. 

The early warning notice is intended to act as notice of events which (1) might happen and (2) have the potential to affect the contract if they do occur.  The contractor is required to provide early warning to the project manager as soon as they become aware of any matter which could increase the contract price, delay completion, delay meeting a key date or otherwise impair performance of the works.  In other words, the contractor cannot hold back notification of issues until the end of the contract.

Similarly, the employer must bring any problems to the contractor's attention at the earliest opportunity.  The NEC4 also provides for parties to attend risk reduction meetings to address how to reduce the effect of the notified risks.

The contractor may also give an early warning to the project manager of any other matters which could increase the total cost.  The project manager may give the same warning if they become aware of any matter which could increase the contractor's total cost.

As such, an early warning notice should be given as soon as a contractor is aware of any matter which could result in increased costs, delay or impair the performance of the works.

Next week we will consider compensation events under the NEC form of contract.  If you haven’t read our previous delay blogs, they can be found here.

Should you require assistance with any aspect of a construction contract, we have a large and experienced construction team who would be happy to discuss this with you.

Disclaimer

The content of this webpage is for information only and is not intended to be construed as legal advice and should not be treated as a substitute for specific advice. Morton Fraser LLP accepts no responsibility for the content of any third party website to which this webpage refers.  Morton Fraser LLP is authorised and regulated by the Financial Conduct Authority.